Warehouse Inspection Checklist: What to Check on Site before You Lease

A site-visit checklist for leasing a warehouse in India: approach road, docks, clear height, floor, roof, drainage, power, fire systems and labour catchment.

In Short

Before leasing a warehouse, inspect eight things in person: the approach road, truck yard and docks, usable clear height, floor, roof and drainage, power and water, fire systems as installed, and surroundings including labour and security. Plan two to three hours for 50,000 sq ft. A fail on road access, flooding or power usually rules a building out.

A warehouse inspection before leasing should cover eight things you can only judge in person: the approach road, the truck yard and docks, clear height, the floor, the roof and drainage, power and water, the fire systems as installed, and the surroundings, including labour and security. Photos and brochures cover none of these reliably. Take a measuring tape, a laser distance meter and this checklist, and plan on two to three hours for a building of 50,000 sq ft. The paperwork (title, land use, fire NOC, licences) is a separate exercise, covered in our warehouse compliance checklist.

Before You Go: What to Ask the Owner For

Ask for these in advance, so the visit is spent checking rather than asking:

  • The site plan and the building drawings, with column spacing marked.
  • The quoted area, and whether it is carpet, built-up or super built-up.
  • The sanctioned electricity load, in kVA, and the latest electricity bill.
  • The fire NOC, with its validity date, and the fire system layout.
  • Any flooding, waterlogging or roof-leak history in the last three monsoons.

Then visit at the time of day your trucks will actually arrive. A road that is clear at 11 am can be jammed at 7 pm.

1. The Approach Road

The route into the site decides whether your trucks arrive at all, and it is the check most often skipped.

CheckHow to check it on siteRed flag
Road widthDrive the last 5 km in a car and note the narrowest pointA single-lane stretch or a village road through a market
Turning inWatch whether a 40-ft container can swing into the gate without reversing on the main roadTrucks have to stop traffic to turn in
Height limitsLook for rail underbridges, flyover ramps and low power lines on the only route inA height or weight restriction with no alternative route
Entry restrictionsAsk the security guard and a nearby shop when trucks are stopped by the policeHeavy-vehicle entry bans at the hours you need
MonsoonAsk neighbours whether the road floods, and look for water marks on wallsThe only access road goes under water every year

2. The Truck Yard and Docks

CheckHow to check it on siteRed flag
Apron depthMeasure from the dock face to the boundary or the nearest obstructionToo shallow for a 40-ft container to dock and pull out
Dock countCount docks and dock levellers, and compare with your peak trucks per hourLevellers "planned", or one leveller shared by many docks
Dock heightMeasure the platform against your usual truck bed heightGround-level loading only, for an operation that needs docks
ParkingLook for space for trucks waiting to be loadedTrucks will queue on the public road
SurfaceWalk the yard for cracks, potholes and pondingBroken concrete or a yard that holds water

Grade A benchmarks for apron depth, dock height and dock density are set out in our Grade A vs B vs C warehouse guide. Use them as the yardstick; do not take the brochure's word for it.

3. Clear Height and the Structure

CheckHow to check it on siteRed flag
Usable clear heightLaser-measure to the lowest obstruction: sprinkler main, duct, beam or light fittingHeight quoted at the ridge rather than under the obstruction
Column spacingMeasure bay widths and check them against your racking layoutColumns land in the middle of your aisles
Structural conditionLook for rusting steel, cracked columns and bent purlinsVisible corrosion or cracks at column bases
Walls and claddingCheck sheeting for gaps, rust and damage at truck heightHoles that let in rain, birds or pests
Ventilation and lightStand in the middle of the floor with the lights off, then onDark racking bays, no ventilation, heat build-up under the roof

The clear height under the obstruction decides how many racking levels you fit, which decides how much the building holds. A shed that loses a metre to a low sprinkler main can lose a whole pallet level across the floor.

Cross-section of a warehouse with a 40-foot container truck backed onto the dock. Clear height quoted at the roof ridge is taller than the usable clear height, which runs from the floor to the lowest obstruction, here a sprinkler main. The low sprinkler main costs a whole pallet level. Dock height is checked against your truck bed, and apron depth is measured from the dock face to the boundary or the nearest obstruction, so a 40-foot container can dock and pull out. Illustrative, not to scale.

4. The Floor

CheckHow to check it on siteRed flag
FlatnessWalk it, roll a ball, or lay a straight edge across jointsVisible undulation or a floor that slopes toward the docks
Cracks and jointsLook for cracked panels, broken joint edges and patch repairsWide cracks, spalled joints, recent patching
Load ratingAsk for the rated load in tonnes per square metre, in writingNo figure available, for an operation with heavy racking
FinishCheck whether the surface dusts when scuffedA dusting floor that will need coating before use
Plinth levelCompare the floor level with the road and the yardFloor at or below road level, which invites flooding

5. The Roof and Drainage

CheckHow to check it on siteRed flag
Roof leaksLook up for daylight and down for stains on the floorWater stains under the roof sheets or buckets on the floor
GuttersCheck gutters and downpipes are sized, clear and connectedDownpipes that discharge onto the yard or into the building
StormwaterWalk the boundary for drains and find out where they goNo stormwater drain, or one that backs up from the road
Waterlogging historyAsk the owner, the guard and a neighbour, separatelyStories that do not match

A monsoon that puts 15 cm of water on the floor can take out a whole season of inventory. If the answers on flooding differ, believe the neighbour.

6. Power and Water

CheckHow to check it on siteRed flag
Sanctioned loadMatch the kVA on the electricity bill with your equipment and lighting loadA load too small for your forklift charging or cold rooms
TransformerFind it, and ask whether it is dedicated or sharedA shared transformer with no plan to upgrade
Backup powerCheck the generator's capacity and whether it is in working orderNo generator, or one that has not run in months
WaterCheck the supply source and the storage tank capacityTanker-only water with no storage
Toilets and amenitiesCount toilets and check a changing room and canteen space existFacilities too small for your shift headcount

Upgrading a sanctioned load is slow and costly, so find out now whether the building has the power you need, not after you have signed.

7. Fire Systems, as Installed

The fire NOC is a document. This check is about whether the equipment behind it exists and works.

CheckHow to check it on siteRed flag
HydrantsWalk the ring main and open a hydrant valve cabinetEmpty cabinets, missing hoses, rusted valves
SprinklersCheck coverage across the whole floor, including under mezzaninesSprinklers only near the office, or heads painted over
Pump roomAsk to see the pumps startedPumps that do not start, or a diesel pump with no fuel
Water tankCheck the fire tank is full and dedicatedA fire tank that doubles as the domestic supply
Exits and extinguishersCheck exits are clear and extinguishers are in dateBlocked exits and expired extinguishers

8. The Surroundings, Labour and Security

CheckHow to check it on siteRed flag
NeighboursLook at what the adjoining plots are used forA chemical unit, scrapyard or open burning next door
Labour catchmentAsk where local workers live and what shift wages areNo workforce within commuting distance
Public transportCheck for a bus stop or shared-auto route within walking distanceStaff will need company transport for every shift
SecurityCheck the boundary wall, gate, lighting and CCTVLow or broken walls, dark boundaries at night
Mobile networkCheck signal and data speed inside the buildingNo signal on the floor, which breaks handheld scanners
Local issuesAsk about labour unions, local contractor demands and past disputes"You will have to use our people for loading"

After the Visit: Turn Notes into a Decision

Score each of the eight sections as pass, fixable or fail. For every "fixable", get the fix written into the term sheet: who does it, by when, and at whose cost. A single "fail" on the approach road, flooding or power is usually enough to drop a warehouse, whatever the rent. Only once a building clears the site check is it worth moving on to the paperwork and to comparing rent quotes on effective cost, which our guide to comparing warehouse rent quotes walks through.

Written by Nihas MKH · Updated

Back to top

Frequently Asked Questions

Check the approach road, the truck yard and docks, the usable clear height, the floor, the roof and drainage, the power and water supply, the fire systems as installed, and the surroundings, including labour and security. These are the things photographs and brochures cannot show you.

Use a laser distance meter to measure from the floor to the lowest obstruction, such as a sprinkler main, duct or beam, not to the roof ridge. That lower figure decides how many racking levels you can actually fit.

For a warehouse of around 50,000 sq ft, plan on two to three hours on site, plus a drive along the approach route at the hour your trucks will use it. Ask for drawings, the power bill and the fire NOC in advance so the visit is spent checking.

An approach road that trucks cannot use reliably, whether through width, height limits, entry bans or monsoon flooding. The building can be fixed; the road usually cannot, and it affects every truck for the whole lease.

No. The NOC is the approval; you still need to see that the hydrants, sprinklers, pumps and water tank are installed and working. Insurers look at both, and a warehouse with a valid NOC and a dry fire tank is still a risk. WareOnGo physically verifies every warehouse before it reaches your shortlist, so the first site visit you make is to buildings that have already passed the basics. Tell us your requirement at sales@wareongo.com.