Warehouse Inspection Checklist: What to Check on Site before You Lease
A site-visit checklist for leasing a warehouse in India: approach road, docks, clear height, floor, roof, drainage, power, fire systems and labour catchment.
In Short
Before leasing a warehouse, inspect eight things in person: the approach road, truck yard and docks, usable clear height, floor, roof and drainage, power and water, fire systems as installed, and surroundings including labour and security. Plan two to three hours for 50,000 sq ft. A fail on road access, flooding or power usually rules a building out.
A warehouse inspection before leasing should cover eight things you can only judge in person: the approach road, the truck yard and docks, clear height, the floor, the roof and drainage, power and water, the fire systems as installed, and the surroundings, including labour and security. Photos and brochures cover none of these reliably. Take a measuring tape, a laser distance meter and this checklist, and plan on two to three hours for a building of 50,000 sq ft. The paperwork (title, land use, fire NOC, licences) is a separate exercise, covered in our warehouse compliance checklist.
Before You Go: What to Ask the Owner For
Ask for these in advance, so the visit is spent checking rather than asking:
- The site plan and the building drawings, with column spacing marked.
- The quoted area, and whether it is carpet, built-up or super built-up.
- The sanctioned electricity load, in kVA, and the latest electricity bill.
- The fire NOC, with its validity date, and the fire system layout.
- Any flooding, waterlogging or roof-leak history in the last three monsoons.
Then visit at the time of day your trucks will actually arrive. A road that is clear at 11 am can be jammed at 7 pm.
1. The Approach Road
The route into the site decides whether your trucks arrive at all, and it is the check most often skipped.
| Check | How to check it on site | Red flag |
|---|---|---|
| Road width | Drive the last 5 km in a car and note the narrowest point | A single-lane stretch or a village road through a market |
| Turning in | Watch whether a 40-ft container can swing into the gate without reversing on the main road | Trucks have to stop traffic to turn in |
| Height limits | Look for rail underbridges, flyover ramps and low power lines on the only route in | A height or weight restriction with no alternative route |
| Entry restrictions | Ask the security guard and a nearby shop when trucks are stopped by the police | Heavy-vehicle entry bans at the hours you need |
| Monsoon | Ask neighbours whether the road floods, and look for water marks on walls | The only access road goes under water every year |
2. The Truck Yard and Docks
| Check | How to check it on site | Red flag |
|---|---|---|
| Apron depth | Measure from the dock face to the boundary or the nearest obstruction | Too shallow for a 40-ft container to dock and pull out |
| Dock count | Count docks and dock levellers, and compare with your peak trucks per hour | Levellers "planned", or one leveller shared by many docks |
| Dock height | Measure the platform against your usual truck bed height | Ground-level loading only, for an operation that needs docks |
| Parking | Look for space for trucks waiting to be loaded | Trucks will queue on the public road |
| Surface | Walk the yard for cracks, potholes and ponding | Broken concrete or a yard that holds water |
Grade A benchmarks for apron depth, dock height and dock density are set out in our Grade A vs B vs C warehouse guide. Use them as the yardstick; do not take the brochure's word for it.
3. Clear Height and the Structure
| Check | How to check it on site | Red flag |
|---|---|---|
| Usable clear height | Laser-measure to the lowest obstruction: sprinkler main, duct, beam or light fitting | Height quoted at the ridge rather than under the obstruction |
| Column spacing | Measure bay widths and check them against your racking layout | Columns land in the middle of your aisles |
| Structural condition | Look for rusting steel, cracked columns and bent purlins | Visible corrosion or cracks at column bases |
| Walls and cladding | Check sheeting for gaps, rust and damage at truck height | Holes that let in rain, birds or pests |
| Ventilation and light | Stand in the middle of the floor with the lights off, then on | Dark racking bays, no ventilation, heat build-up under the roof |
The clear height under the obstruction decides how many racking levels you fit, which decides how much the building holds. A shed that loses a metre to a low sprinkler main can lose a whole pallet level across the floor.

4. The Floor
| Check | How to check it on site | Red flag |
|---|---|---|
| Flatness | Walk it, roll a ball, or lay a straight edge across joints | Visible undulation or a floor that slopes toward the docks |
| Cracks and joints | Look for cracked panels, broken joint edges and patch repairs | Wide cracks, spalled joints, recent patching |
| Load rating | Ask for the rated load in tonnes per square metre, in writing | No figure available, for an operation with heavy racking |
| Finish | Check whether the surface dusts when scuffed | A dusting floor that will need coating before use |
| Plinth level | Compare the floor level with the road and the yard | Floor at or below road level, which invites flooding |
5. The Roof and Drainage
| Check | How to check it on site | Red flag |
|---|---|---|
| Roof leaks | Look up for daylight and down for stains on the floor | Water stains under the roof sheets or buckets on the floor |
| Gutters | Check gutters and downpipes are sized, clear and connected | Downpipes that discharge onto the yard or into the building |
| Stormwater | Walk the boundary for drains and find out where they go | No stormwater drain, or one that backs up from the road |
| Waterlogging history | Ask the owner, the guard and a neighbour, separately | Stories that do not match |
A monsoon that puts 15 cm of water on the floor can take out a whole season of inventory. If the answers on flooding differ, believe the neighbour.
6. Power and Water
| Check | How to check it on site | Red flag |
|---|---|---|
| Sanctioned load | Match the kVA on the electricity bill with your equipment and lighting load | A load too small for your forklift charging or cold rooms |
| Transformer | Find it, and ask whether it is dedicated or shared | A shared transformer with no plan to upgrade |
| Backup power | Check the generator's capacity and whether it is in working order | No generator, or one that has not run in months |
| Water | Check the supply source and the storage tank capacity | Tanker-only water with no storage |
| Toilets and amenities | Count toilets and check a changing room and canteen space exist | Facilities too small for your shift headcount |
Upgrading a sanctioned load is slow and costly, so find out now whether the building has the power you need, not after you have signed.
7. Fire Systems, as Installed
The fire NOC is a document. This check is about whether the equipment behind it exists and works.
| Check | How to check it on site | Red flag |
|---|---|---|
| Hydrants | Walk the ring main and open a hydrant valve cabinet | Empty cabinets, missing hoses, rusted valves |
| Sprinklers | Check coverage across the whole floor, including under mezzanines | Sprinklers only near the office, or heads painted over |
| Pump room | Ask to see the pumps started | Pumps that do not start, or a diesel pump with no fuel |
| Water tank | Check the fire tank is full and dedicated | A fire tank that doubles as the domestic supply |
| Exits and extinguishers | Check exits are clear and extinguishers are in date | Blocked exits and expired extinguishers |
8. The Surroundings, Labour and Security
| Check | How to check it on site | Red flag |
|---|---|---|
| Neighbours | Look at what the adjoining plots are used for | A chemical unit, scrapyard or open burning next door |
| Labour catchment | Ask where local workers live and what shift wages are | No workforce within commuting distance |
| Public transport | Check for a bus stop or shared-auto route within walking distance | Staff will need company transport for every shift |
| Security | Check the boundary wall, gate, lighting and CCTV | Low or broken walls, dark boundaries at night |
| Mobile network | Check signal and data speed inside the building | No signal on the floor, which breaks handheld scanners |
| Local issues | Ask about labour unions, local contractor demands and past disputes | "You will have to use our people for loading" |
After the Visit: Turn Notes into a Decision
Score each of the eight sections as pass, fixable or fail. For every "fixable", get the fix written into the term sheet: who does it, by when, and at whose cost. A single "fail" on the approach road, flooding or power is usually enough to drop a warehouse, whatever the rent. Only once a building clears the site check is it worth moving on to the paperwork and to comparing rent quotes on effective cost, which our guide to comparing warehouse rent quotes walks through.
Written by Nihas MKH · Updated
Back to topFrequently Asked Questions
Check the approach road, the truck yard and docks, the usable clear height, the floor, the roof and drainage, the power and water supply, the fire systems as installed, and the surroundings, including labour and security. These are the things photographs and brochures cannot show you.
Use a laser distance meter to measure from the floor to the lowest obstruction, such as a sprinkler main, duct or beam, not to the roof ridge. That lower figure decides how many racking levels you can actually fit.
For a warehouse of around 50,000 sq ft, plan on two to three hours on site, plus a drive along the approach route at the hour your trucks will use it. Ask for drawings, the power bill and the fire NOC in advance so the visit is spent checking.
An approach road that trucks cannot use reliably, whether through width, height limits, entry bans or monsoon flooding. The building can be fixed; the road usually cannot, and it affects every truck for the whole lease.
No. The NOC is the approval; you still need to see that the hydrants, sprinklers, pumps and water tank are installed and working. Insurers look at both, and a warehouse with a valid NOC and a dry fire tank is still a risk. WareOnGo physically verifies every warehouse before it reaches your shortlist, so the first site visit you make is to buildings that have already passed the basics. Tell us your requirement at sales@wareongo.com.